Please view the color diagram below to determine each Phase and corresponding tentative schedule.
PHASE I
OPEN
Fiber Miles: 183
Meters: 2245
PHASE II
(Summer 2023)
Fiber Miles: 88
Meters: 3297
PHASE III
(Winter 2023)
Fiber Miles: 191
Meters: 2189
PHASE IV
(2024)
Fiber Miles: 238
Meters: 2357
How soon will I get Connected? We are building a new fiber optic network from start to finish. A project of this size is being broken down into Phases and sub-zones as we work through the multi-year build-out. Breaking each phase of the construction down into smaller zones allows us to have multiple contractors working on different stages of the process as we work the complete the Fiber-to-the-Home (FTTH) project. Through doing this we are able to manage your expectations, as well as provide you location-based updates as we reach your specific area.